27 October 2019
27 October 2019 The dining table and chairs have been delivered and put in place. The light shades have been put up, and the mirror, “Grandma”, and other paintings and prints have been hung on the dining area ‘long wall’.
27 October 2019 The dining table and chairs have been delivered and put in place. The light shades have been put up, and the mirror, “Grandma”, and other paintings and prints have been hung on the dining area ‘long wall’.
27 October 2019 The dining table and chairs have been delivered and put in place. The light shades have been put up, and the mirror, paintings and prints hung on the dining area ‘long wall’.
11 November 2019 Building Control has approved the revised foundation depth and the waterfilled trenches have been pumped out. The concrete pour is now taking place, amidst extremely wet conditions.
27 October 2019 The furniture has been added to the room, and the design is now complete, with the exception of the paintings and prints on the walls.
7 October 2019 The flooring and the stair carpet together. Skirting and architraves fitted, and the shelving almost complete. Note the void behind the skirting at the base of the shelves concealing the heating pipes.
4 October 2019 The finished floor. And a clean Muddy Dog.
3 October 2019 The rear garden lounge has now been fully plastered and painted, and the concrete floor is now being prepared for the new flooring. The area has had a levelling compound applied to accept a heavy duty pvc in a timber parquet design was chosen to add [...]
5 November 2019 The foundations have now been excavated and are awaiting Building Control approval. However, the weather conditions and the imperviousness of the ground have resulted in the trenches being completely filled with rainwater, and pumping out will commence later this week. Clearly, the proposed soakaway will not [...]