5 November 2019

The foundations have now been excavated and are awaiting Building Control approval. However, the weather conditions and the imperviousness of the ground have resulted in the trenches being completely filled with rainwater, and pumping out will commence later this week.

Clearly, the proposed soakaway will not be possible and surface water drainage has been redesigned to allow for a connection into the existing system.